Site icon Saptakala Real Estate Law Journal

MahaRERA Pulls Up Builders for 10-Year Delay in Project

MahaRERA

In a strong order reinforcing homebuyer rights under the Real Estate (Regulation and Development) Act, 2016 (RERA), the Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed Borivali-based Swadhinta Builders LLP to revive its stalled housing project “Shri Vallabh Residency” and compensate three homebuyers for an extraordinary delay exceeding a decade.

The authority also ordered the developer to pay statutory interest for delayed possession, after noting that each complainant had paid ₹7.5 lakh as booking amount in 2010, yet neither possession nor registered agreements were executed.

Background of the Dispute

Three separate online complaints were filed before MahaRERA on February 28, 2025, by aggrieved homebuyers who had booked flats in 2010.

According to the complainants:

The project was later registered under MahaRERA, but the developer allegedly unilaterally obtained extensions without resolving pending buyer claims.

Assurances Given Under Allotment Letters

As per Clause 9 of the allotment letter, possession was promised within 30 months from:

Key dates highlighted in the complaint:

Despite these milestones, the developer failed to:

Developer’s Defence Rejected

Swadhinta Builders opposed the complaints, arguing that they were time-barred and questioning why the complainants had delayed seeking legal remedy.

However, MahaRERA rejected this argument. The authority referred to an earlier Appellate Tribunal order passed in similar cases involving the same developer and similarly placed allottees.

MahaRERA observed that:

The authority clarified that since the earlier appellate order remains valid and binding, it cannot take a divergent view in the present case.

Importantly, MahaRERA held that the issue of delay in filing complaints does not carry legal substance, particularly when rights under Section 13 of RERA (mandatory execution of registered Agreement for Sale) are involved.

Key Directions Issued by MahaRERA

While allowing the complaints, MahaRERA directed the developer to:

The order reinforces that promoters cannot avoid statutory obligations by delaying project revival or citing technical objections such as limitation.

Significance of the Order

This ruling is significant because it:

For homebuyers who booked flats before RERA came into force but continue to suffer due to non-execution of agreements and non-delivery of possession, this decision sends a clear message — statutory rights under RERA remain enforceable.

The order also underscores that developers cannot retain booking amounts for years without executing formal agreements or progressing construction.

Exit mobile version