The National Consumer Disputes Redressal Commission (NCDRC) has directed a Mumbai-based builder to pay ₹6 crore in compensation to a cooperative housing society after holding the developer responsible for failing to obtain the Occupation Certificate (OC) for more than two decades.
The Commission found that the society’s members had been living under a continuing risk of demolition because the construction carried out by the developer was allegedly in excess of or contrary to the sanctioned plans, resulting in the authorities refusing or resisting the grant of the Occupation Certificate.
In its judgment pronounced on August 17, 2026, the NCDRC also directed the builder to obtain the Occupation Certificate within 12 months and hand it over to the society and its members.
The builder was additionally directed to pay ₹10 lakh towards litigation costs.
Redevelopment Agreement Was Executed in 2005
The dispute arose from the redevelopment of Balaji Apartments in Santa Cruz, Mumbai, involving Tirupati Devi Cooperative Housing Society.
The society comprised 33 members occupying 25 flats in two wings of the building.
The society had entered into a redevelopment agreement with Raja Construction Company on March 14, 2005.
Under the redevelopment arrangement, the developer was required to:
- Demolish the existing buildings;
- Construct new buildings;
- Provide flats to the existing members;
- Obtain the required Occupation Certificate;
- Obtain the necessary approvals; and
- Provide a new water connection.
The developer subsequently handed over possession of the redeveloped flats from 2008 onwards.
However, according to the society, possession was handed over without providing important documents and facilities, including the sanctioned building plans, Completion Certificate, Occupation Certificate and new water connections.
Construction Allegedly Did Not Match Sanctioned Plans
The dispute became more serious after the society obtained information through an RTI application.
According to the society, it came to know that the construction did not conform to the sanctioned plans.
The society alleged that additional construction had been carried out, and that this became one of the reasons why the authorities did not grant the Occupation Certificate.
The absence of an OC created a continuing uncertainty regarding the legal status of the construction and the members’ occupation of their homes.
The society therefore approached the NCDRC in 2013, seeking compensation for the delay and other deficiencies, including differences in flat areas, regularisation charges and failure to provide the necessary statutory certificates.
Builder Blamed Flat Owners for Illegal Changes
The developer disputed the allegations and also raised an objection regarding the delay in filing the complaint.
The builder claimed that some of the flat owners themselves had carried out illegal alterations in their respective flats and suggested that these changes were responsible for the failure to obtain the Occupation Certificate.
The NCDRC, however, found no evidence supporting the builder’s allegation that the members had carried out illegal construction in their individual units.
The Commission also noted that the developer had itself undertaken to provide the members with additional carpet area and had accepted responsibility for obtaining the Occupation Certificate and completing the necessary formalities.
NCDRC Holds Developer Responsible for Obtaining OC
The bench comprising NCDRC President A.P. Sahi and Member Bharatkumar Pandya held that the developer could not escape responsibility for the absence of the Occupation Certificate.
The Commission observed that although the members had been enjoying possession since 2008, the legality of the extent of construction and their possession remained in jeopardy because part of the construction was allegedly in excess of or contrary to the approved plans.
The Commission emphasised that the developer was responsible for:
Preparing proper plans, constructing according to those plans and obtaining the required approvals.
The NCDRC rejected the contention that the members were responsible for the situation.
It observed that there was no evidence that the members had made illegal construction in their units and noted that it was the developer who had promised, constructed and handed over the flats with additional carpet area.
Absence of OC Created a Continuing Cause of Anxiety
One of the most significant aspects of the judgment is the Commission’s treatment of the prolonged absence of the Occupation Certificate.
The issue was not treated as a problem that ended when possession was handed over.
Instead, the NCDRC found that the failure to obtain the OC had become a continuing problem for the society and its members.
The members had been living with uncertainty over the legality of the construction and the possibility of demolition or adverse action by the authorities for more than 20 years.
The Commission considered this prolonged uncertainty, anxiety, mental agony and hardship while determining compensation.
₹6 Crore Compensation Awarded
The redevelopment agreement itself contained a compensation provision.
Under the agreement, the developer was required to pay ₹1 lakh per month if the project was not completed within the stipulated period of 24 months.
The NCDRC, however, considered the extraordinary delay and the continuing risk faced by the society and its members and enhanced the stipulated rate to 1.5 times.
The enhanced compensation was calculated for the period from June 2008 to August 2026, resulting in compensation of approximately ₹3.24 crore.
The Commission additionally awarded ₹26 lakh towards the hardship and expenses associated with the absence of a municipal water connection and additional municipal taxes.
It then awarded a further ₹2.5 crore, taking the overall compensation to:
₹6 Crore
The Commission considered this amount just and fair in view of the long-standing deficiency, continuing uncertainty and mental agony suffered by the society and its members.
Builder and Partners Held Jointly and Severally Liable
The NCDRC held the builder and its partners jointly and severally responsible for the deficiency in service.
This means that the liability to satisfy the compensation award was not confined to one particular individual respondent.
The respondents were directed to pay the ₹6 crore compensation within three months.
If the amount is not paid within the stipulated period, it will carry 8% simple interest until the entire amount is paid.
Builder Given 12 Months to Obtain Occupation Certificate
The NCDRC did not restrict the relief to monetary compensation.
It also issued a specific direction requiring the builder to take steps to resolve the underlying problem.
The developer has been directed to:
Obtain the Occupation Certificate within 12 months, pay all necessary charges for obtaining it and hand over the OC to the housing society and its 33 current members.
The builder has also been ordered to pay ₹10 lakh as litigation costs within three months.
Possession Without OC Can Create Serious Legal Problems
The judgment highlights an important issue for members of redeveloped cooperative housing societies.
Physical possession of a flat does not necessarily resolve all obligations of a developer.
A society may receive possession of its flats but still face serious difficulties if the developer has failed to complete the statutory approval process.
An Occupation Certificate provides important confirmation regarding the authorised and permissible occupation of a completed building.
Where a developer hands over flats without obtaining the necessary approvals, members may continue to face uncertainty concerning the legality of the construction and their occupation.
Additional Construction Cannot Simply Be Passed on to Homebuyers
The case also demonstrates the risks associated with construction beyond sanctioned plans.
The NCDRC’s findings, as described in the order, indicate that where the developer undertakes additional construction or additional carpet area as part of the redevelopment arrangement, the developer cannot subsequently shift responsibility for the consequences to the individual flat owners without evidence establishing that the members themselves caused the violations.
The responsibility of the developer to construct in accordance with approved plans and obtain statutory approvals remains an important part of the redevelopment obligation.
A Significant Judgment for Cooperative Housing Societies
The NCDRC judgment is particularly significant for cooperative housing societies undergoing redevelopment.
Redevelopment does not end with the physical construction of the new building or the handing over of flats.
Developers must also complete the necessary statutory formalities and ensure that the society receives the documents, approvals and facilities promised under the redevelopment agreement.
The case demonstrates that the failure to obtain an OC can have consequences extending for years after possession has been handed over.
For society members, the absence of an OC can affect not only the legality of occupation but also create financial, administrative and legal uncertainty.
Key Takeaways for Housing Societies and Homebuyers
1. Possession Is Not the End of the Developer’s Obligations
A developer’s responsibilities may continue even after possession has been handed over if statutory approvals and promised facilities remain outstanding.
2. Occupation Certificate Is Crucial
An OC is an important document confirming the authorised occupation of the completed building. Societies should ensure that the developer obtains and hands over the required certificate.
3. Sanctioned Plans Must Be Followed
Developers are expected to construct according to the sanctioned plans and approved specifications. Deviations can create serious problems for flat owners.
4. Redevelopment Agreements Should Clearly Define Responsibilities
A redevelopment agreement should specifically identify who will obtain the OC, Completion Certificate, water connection, approvals and other statutory documents.
5. Long-Standing Deficiencies Can Have Continuing Consequences
The NCDRC’s award shows that a failure continuing over many years can result in substantial compensation where it causes continuing hardship and uncertainty.
6. Society Members Should Preserve Documents
Housing societies should maintain copies of the redevelopment agreement, sanctioned plans, approvals, correspondence, possession documents, municipal communications and other records concerning the project.
NCDRC’s Message to Developers
The judgment sends a strong message that developers cannot treat the handing over of physical possession as the completion of their obligations.
Where a developer has undertaken responsibility for obtaining statutory approvals, failure to do so can leave homebuyers and society members exposed to serious consequences.
In the present case, the NCDRC found that the absence of the Occupation Certificate had left the members facing the continuing risk of demolition for more than 20 years.
The ₹6 crore compensation, coupled with the direction to obtain the OC within 12 months, therefore represents a significant finding of responsibility against the developer.
Conclusion
The NCDRC’s August 17, 2026 judgment is an important reminder that redevelopment obligations extend beyond constructing and handing over new flats.
A developer must ensure that the construction is carried out in accordance with the approved plans and that the required statutory approvals, including the Occupation Certificate, are obtained.
For the members of Tirupati Devi Cooperative Housing Society, the failure to obtain the OC continued to create uncertainty long after they had taken possession of their homes.
By awarding ₹6 crore in compensation, directing the builder to obtain the OC within 12 months, and imposing ₹10 lakh in litigation costs, the NCDRC has recognised the serious consequences that can arise when a redevelopment project remains without the necessary statutory approval for decades.

