Site icon Saptakala Real Estate Law Journal

RERA Dismisses Homebuyer’s Compensation Claim Despite Delay in Possession

Punjab RERA

In a significant ruling interpreting the provisions of the Real Estate (Regulation and Development) Act, 2016 (RERA), the Punjab Real Estate Regulatory Authority (Punjab RERA) has dismissed a homebuyer’s claim seeking compensation, interest, and litigation expenses for delayed possession of an apartment after holding that the buyer had accepted possession and continued with the project.

The Authority observed that under Section 18 of the RERA Act, a homebuyer who chooses to remain in the project after taking possession cannot seek compensation in the manner claimed under the complaint. Instead, such buyers are entitled only to remedies specifically provided under the Act, subject to the appropriate legal forum.

Background of the Case

The complaint was filed by Baljit Singh Mahal against Sushma Buildtech Ltd. regarding an apartment in the Sushma Chandigarh Grande residential project located at Zirakpur, Punjab.

According to the complaint:

The complainant alleged that the prolonged delay caused him significant financial loss, mental harassment, and additional expenses. Accordingly, he approached Punjab RERA seeking compensation, delayed possession interest, and litigation costs.

Builder Defended the Delay

Sushma Buildtech opposed the complaint and submitted that the homebuyer had:

The developer further argued that the delay was covered under force majeure circumstances, including the disruption caused by the COVID-19 pandemic, and maintained that it had fulfilled all contractual obligations after handing over possession.

Punjab RERA’s Interpretation of Section 18

After examining the facts and the provisions of the RERA Act, Punjab RERA observed that Section 18 creates two distinct categories of homebuyers.

Homebuyers Who Withdraw from the Project

Where an allottee chooses to withdraw because of delayed possession, the buyer may seek:

Homebuyers Who Continue with the Project

Where an allottee accepts possession and continues with the project, the available remedy is different.

Punjab RERA held that such buyers are generally entitled to claim interest for the delayed possession, but not compensation in the manner sought in the present proceedings under Section 18.

Reliance on Supreme Court Judgment

The Authority relied upon the landmark judgment of the Supreme Court in M/s Newtech Promoters and Developers Pvt. Ltd. vs State of Uttar Pradesh.

The Supreme Court had clarified that claims relating to delayed-possession interest and claims for compensation are separate statutory remedies under the RERA Act, each governed by different provisions and authorities.

Relying upon this principle, Punjab RERA concluded that the complainant’s claim was not maintainable before it in the form presented.

Complaint Held Not Maintainable

Since the complainant had:

Punjab RERA held that the complaint seeking compensation, interest, and litigation expenses under Section 18 could not be entertained.

Accordingly, the Authority dismissed the complaint.

Liberty Granted to Pursue Appropriate Legal Remedy

Although the complaint was dismissed, Punjab RERA granted liberty to both parties to pursue any other remedy available under law before the competent authority, if applicable.

The Authority did not decide upon the merits of any such future claim.

Important Takeaway for Homebuyers

The ruling highlights an important distinction under the RERA Act.

A homebuyer’s legal remedy largely depends upon whether the buyer:

Before accepting possession in a delayed project, homebuyers should carefully understand the legal implications under Section 18 of RERA and seek professional legal advice wherever necessary.

The decision also reiterates the importance of relying on the appropriate statutory remedy available under the RERA framework rather than assuming that every delayed possession automatically results in compensation.

Exit mobile version