RERA Orders Ramky Estates to Refund, Says Fit-Out Possession Without OC Is Illegal

Refund for Delayed Possession

The Telangana Real Estate Regulatory Authority (TG RERA) passed a significant order against Ramky Estates and Farms Ltd. in a complaint filed by homebuyers K. Sravanthi and K. Bhanu Prakash concerning an apartment in the Ramky One Symphony project at Patancheru, Hyderabad.

The buyers had booked a 1,585 sq. ft. apartment and executed an Agreement for Sale on July 26, 2022. The total consideration for the apartment was approximately ₹1.03 crore, out of which the buyers had already paid ₹98.05 lakh.

As per the agreement, the developer promised to hand over possession by September 30, 2025.

However, when the promised possession date arrived, the builder had not obtained the Occupancy Certificate (OC) from the competent authority.

Homebuyers Exercised Their Right to Seek Refund

Since the Occupancy Certificate had not been obtained by the promised possession date, the homebuyers chose to withdraw from the project and sought a refund under the provisions of the Real Estate (Regulation and Development) Act, 2016 (RERA).

The buyers argued that without an Occupancy Certificate, the project could not be considered legally complete and therefore the possession offered by the developer was invalid.

Builder’s Defence Before TG RERA

Ramky Estates contended that:

The developer argued that the delay in obtaining the OC should not result in refund liability.

TG RERA Rejects Builder’s Arguments

TG RERA categorically rejected the builder’s defence and held that:

Possession cannot be legally offered without first obtaining an Occupancy Certificate.

The Authority observed that merely allowing buyers to undertake interior work or giving fit-out possession does not amount to lawful possession under the RERA Act.

According to TG RERA:

Fit-out possession without an Occupancy Certificate has no legal recognition under the Real Estate (Regulation and Development) Act, 2016.

Importance of Occupancy Certificate Under RERA

An Occupancy Certificate (OC) is issued by the local authority certifying that:

Without an Occupancy Certificate:

Section 18 of the RERA Act Gives Buyers the Right to Refund

TG RERA relied on Section 18(1)(a) of the RERA Act, which provides that:

If the promoter fails to complete or is unable to give possession in accordance with the terms of the agreement, the allottee has the right to withdraw from the project and receive a refund along with interest.

The Authority also relied upon the Supreme Court judgment in:

M/s Newtech Promoters and Developers Pvt. Ltd. vs State of Uttar Pradesh

The Supreme Court held that:

TG RERA’s Final Directions

The Authority directed Ramky Estates and Farms Ltd. to:

Refund Amount

₹98,05,087

Interest Payable

10.70% per annum

Interest Period

From September 30, 2025, until the actual date of payment.

Why This Order Is Significant

The decision is important because it clearly establishes that:

1. Occupancy Certificate Is Mandatory

A builder cannot claim project completion without obtaining an Occupancy Certificate.

2. Fit-Out Possession Is Not Legal Possession

Allowing buyers to carry out interior work does not satisfy the builder’s obligation under RERA.

3. Homebuyers Can Withdraw from Delayed Projects

If possession is not delivered as promised, buyers can seek refund with interest.

4. Developers Cannot Escape Liability Due to Procedural Delays

Internal administrative or procedural delays in obtaining approvals cannot deprive buyers of their statutory rights.

Impact on Real Estate Sector

The order sends a strong message to developers that:

For homebuyers, the ruling reinforces confidence that RERA authorities will protect purchasers against delayed possession and incomplete projects.

Conclusion

The TG RERA order against Ramky Estates is another landmark ruling strengthening the rights of homebuyers under the RERA framework. By holding that fit-out possession without an Occupancy Certificate is not valid possession, the Authority has reaffirmed that builders must strictly comply with statutory requirements before handing over apartments.

The ruling also reinforces that homebuyers are entitled to refund and interest when developers fail to deliver possession within the agreed timeline.