In its order dated November 10, 2026, the authority held that obtaining layout permission from the gram panchayat and the Directorate of Town and Country Planning (DTCP) does not exempt a promoter from the separate requirement of registration under the Real Estate (Regulation and Development) Act, 2016.
The project is located at Indaram gram panchayat in Jayapur mandal, Mancherial district. Rejecting the promoter’s plea that he was unaware of the legal requirement, TG RERA observed that an apology could not absolve him of liability for violating the Act.
The order was passed by TG RERA Members Laxmi Narayana Jannu and K. Srinivasa Rao in a suo motu proceeding initiated following a petition filed by Mohd Naheem Pasha.
Complaint Alleges Sale and Marketing Without RERA Registration
Pasha alleged that the promoter was advertising and selling plots in Sri Nilaya Homes without obtaining registration from TG RERA, despite having secured permissions from the gram panchayat and DTCP.
In support of his allegations, the complainant submitted the project brochure and an encumbrance statement covering the properties sold by the promoter.
The complaint brought the issue of whether planning and layout permissions could be treated as a substitute for the mandatory registration required under Section 3(1) of the RERA Act.
Promoter Relies on DTCP Layout Permission
In his reply dated March 30, 2026, Nelli Srinivas relied on the tentative layout permission obtained from DTCP in 2022.
He informed the authority that plots mortgaged to the gram panchayat had been released after completion of the development works. However, his application for final layout approval was still pending.
The promoter admitted that he had violated the RERA registration requirement. He pleaded ignorance of the law and tendered an apology.
During hearings held on April 21, June 30 and August 19, 2026, Srinivas assured the authority that such a violation would not be repeated. He also submitted that all plots had already been sold and that advertising and marketing activities had been discontinued.
Layout Permission and RERA Registration Are Separate Requirements
Rejecting the promoter’s defence, TG RERA clarified that planning permission and RERA registration are two distinct statutory requirements.
The authority held that neither the layout approval obtained from the planning authorities nor a pending application for final layout approval could establish compliance with Section 3(1) of the RERA Act.
It emphasised that the requirement of registration is mandatory and is intended to promote transparency and accountability in real estate projects, while protecting the interests of prospective allottees.
The promoter’s plea of ignorance and subsequent assurance that the violation would not recur did not absolve him of the consequences of carrying out advertising, marketing and sale activities without registration.
₹5.3 Lakh Penalty to Be Deposited Within 30 Days
Invoking Section 59 of the RERA Act, the authority directed Nelli Srinivas to pay a penalty of ₹5.3 lakh for the violation.
The amount must be deposited into the TG RERA Fund within 30 days from the date of the order, either through a demand draft or by online payment.
The authority further warned that failure to deposit the penalty within the prescribed period would invite further penal action under Section 63 of the Act.
Key Takeaway for Real Estate Promoters
The TG RERA order reinforces the distinction between layout or planning permission and statutory RERA registration. A promoter cannot rely on approvals obtained from local planning authorities to bypass the registration requirement under Section 3(1).
Promoters must ensure that the applicable RERA registration requirements are fulfilled before undertaking advertising, marketing, booking or sale activities covered by the Act. The order also makes clear that claiming ignorance of the law or tendering an apology does not automatically protect a promoter from statutory penalties.