Share this

By Legal Bureau

Maharashtra RERA authority have extended all compliance and date of completion which were falling in March, April and May 2020 till 30th June 2020. In an order 13/2020 dated 2nd April 2020, the Authority have extended all compliance till 30th June 2020. The Order said “For all MahaRERA Registered projects where completion date, revised completion
date or extended completion date expires on or after 15th March 2020, the period of
validity for registration of such projects shall be extended by three months.
MahaRERA shall accordingly issue project registration certificates, with revised
timelines for such projects, at the earliest.”

The Order further state that : “Further, the time limits of all statutory compliance in accordance with the Real
Estate (Regulation and Development) Act, 2016 and the rules and regulations made
there under, which were due in March / April / May are extended to 30th June 2020.”

It means that all the completion dates falling in March, April and May 2020 are automatically extended till 30th June 2020. Also the Authority shall issue a new revised project registration certificate. For all the compliance such as Form 1, 2 and 3 the same is extended till 30th June 2020.

Download Order here: MAHARERADelay

Leave a Reply

Your email address will not be published. Required fields are marked *